Lake Side I - Utah
543 MW 2X1 combined cycle with duct firing using Siemens 501FD combustion turbine generators and Siemens triple pressure steam turbine generator; commercial operation achieved in 2007. Companion project, Lake Side II -580 MW, has nearly completed permitting but is currently on hold pending Client re-bidding of EPC package.